Workshop 30 × 48 m or Workshop 30 × 48 m, frame only?

Both examples are generated with the same parameters; only the walls differs. Quantities include waste, no prices – the generator shows the price from the catalogue. A preliminary result, not a design.

Key facts

ClosedOpen wallsDifference
Footprint30 × 48 m30 × 48 m
Built-up area1,440 m²1,440 m²=
Wall height9 m9 m=
Ridge height11.11 m11.11 m=
Labour hours3,618 h2,766 h−852 h (-24 %)
Material lines2521−4
Materials (incl. waste, incl. VAT)€210,138.00€150,154.49−€59,983.51 (-29 %)

Preliminary prices from catalogue lt-2026-10 (2026-10-25). This is an example, not an offer: supplier prices vary and labour depends on your rate – you enter it and your own materials in the generator. Catalogue prices are still being verified.

Structural engineer approval required

Material quantities

Lines that differ come first; “—” means the material is not used in that variant.

MaterialUnitClosedOpen wallsDifference
C-section girt 150Wallsm992.16—−992.16
Sandwich panel 80 mmExternal claddingm²1,547.89—−1,547.89
Sectional overhead gateOpeningsm²36—−36
C-section girt 150Openingsm19.29—−19.29
Self-drilling screws 35 mmFastenerspcs23,75411,370−12,384
Column anchor bolt setFoundationset2020=
Concrete C20/25Foundationm³5.385.38=
Formwork (boards / panels, rental)Foundationm²28.1628.16=
Crushed stone / gravel 0–32Floorm³306.92306.92=
Concrete C20/25Floorm³219.73219.73=
GeotextileFloorm²1,534.611,534.61=
Rebar mesh 150x150Floorm²1,534.611,534.61=
Column base plate with stiffeners (I-section)Wallspcs2020=
Wind bracing rod Ø16 with turnbucklesWallsm101.15101.15=
HEA 300 I-section (hall column, provisional size)Wallsm187.2187.2=
Roof sandwich panels 100 mmRoofm²1,624.131,624.13=
Wind bracing rod Ø16 with turnbucklesRoofm146.14146.14=
Truss bearing and apex joint set, boltsRoofset77=
Open-web truss (OWJ), welded, provisional sizeRoofm220.63220.63=
Z-section purlin 150Roofm1,061.231,061.23=
Downpipe 100 mmRainwater drainagem94.594.5=
Gutter 150 mmRainwater drainagem102.06102.06=
Gutter bracketRainwater drainagepcs162162=
Anchor bolt M12Fastenerspcs160160=
Post connectorFastenerspcs2121=